Krajnji kupac Opis projekta Platforme, alati i tehnologije Država
1 HEP Proizvodnja d.o.o. Reconstruction of the boiler plant TE Plomin 2 by installing a system for reducing nitrogen oxides in boiler flue gases
CROATIA
2 IPP Delek Ashkelon Ltd. Migration of steam turbine monitoring and control systems (Siemens PCS7 -> Siemens SPPA T3000)
Siemens PCS7, Siemens SPPA T3000
STATE OF ISRAEL
3 Hajr Electricity Production Company Plant management system migration (Honeywell Experion LX -> Siemens SPPA T3000)
Honeywell Experion LX, Siemens SPPA T3000
KINGDOM OF SAUDI ARABIA
4 Hajr Electricity Production Company Plant management system migration (Honeywell Experion LX -> Siemens SPPA T3000)
Honeywell Experion LX, Siemens SPPA T3000
KINGDOM OF SAUDI ARABIA
5 JANAF d.d. Participation in the design, realization and integration of crude oil transport and storage systems
Siemens PCS7, Siemens PCS7 Route Control, Siemens PCS7 Safety Matrix, Siemens S7-400 H
CROATIA
6 Belišće d.d. Modernization of the boiler plant management system of block 3 power plant within the paper factory Belišće d.d.
Siemens PCS7
CROATIA
7 Belišće d.d. Modernization of the boiler plant management system of Block 4 power plant within the paper factory Belišće d.d.
Siemens PCS7
CROATIA
8 HEP Proizvodnja d.o.o. Realization of the system of monitoring and management of de-ashanding and external ash transport TE Plomin 1
Siemens S7-300, Siemens WinCC, Siemens ProTool
CROATIA
9 Javni holding Ljubljana d.o.o. Modernization of turbogenerator management systems 1 (32MW), 2 (32MW) i 3 (50MW)
Siemens SPPA T3000
REPUBLIC OF SLOVENIA
10 HOLCIM d.d. Raw Material Mill Management
Siemens PCS7, CEMAT
CROATIA
11 Sladorana d.o.o. Migration of boiler plant management systems within the sugar factory Sladorana d.o.o. (Siemens SIMATIC STEP5 -> Siemens PCS7)
Siemens S7-400 F/H, Siemens STEP5, Siemens PCS7
CROATIA
12 Sladorana d.o.o. Migration of sugar production management system - refinery (Siemens PCS7 V6 -> Siemens PCS7 V7)
Siemens PCS7
CROATIA
13 Tvornica šećera Osijek d.o.o. Migration of sugar production management system - refinery (Siemens PCS7 V6 -> Siemens PCS7 V8)
Siemens PCS7
CROATIA
14 Sladorana d.o.o. Realization of C product management system
Siemens PCS7
CROATIA
15 Sladorana d.o.o. Implementation of sugar crystallization control system
Siemens PCS7
CROATIA
16 JP Elektroprivreda BiH d.d. Realization of boiler plant control system of block 3 thermal power plant Kakanj (relay technology -> Siemens TXP)
Siemens Teleperm XP (TXP)
REPUBLIC OF BOSNIA AND HERZEGOVINA
17 JP Elektroprivreda BiH d.d. Replacement of boiler plant control system of block 7 thermal power plant Kakanj (EI Turbodem - Siemens TXP)
Siemens Teleperm XP (TXP)
REPUBLIC OF BOSNIA AND HERZEGOVINA
18 Javni holding Ljubljana d.o.o. Secondary control system TE-TOL
Siemens SPPA T3000
REPUBLIC OF SLOVENIA
19 HEP Proizvodnja d.o.o. Secondary regulation system of HE Vinodol
Siemens S7-300, WinCC, WinCC Flexible
CROATIA
20 JP Komunalno Brčko d.o.o. Realization of the system of management of the process of pumping, processing and distribution of drinking water in city Brčko (Water factory Brčko)
Siemens S7-300, WinCC
REPUBLIC OF BOSNIA AND HERZEGOVINA
21 HEP Proizvodnja d.o.o. Migration of de-sealing and external ash transport management systems TE Plomin 2 (Siemens SIMATIC STEP5 -> Siemens TXP)
Siemens STEP5, Siemens Teleperm XP (TXP)
CROATIA
22 HEP Proizvodnja d.o.o. Relization of the steam turbine protection system of TE Plomin 1
Siemens S7-400 F/H
CROATIA
23 Termoelektrana Šoštanj d.o.o. Realization of soot block 5 exhaust control system TE Šoštanj
Siemens S7-400
REPUBLIC OF SLOVENIA
24 Javni holding Ljubljana d.o.o. Migration of thermal station management system TE-TOL (Siemens SIMATIC STEP7 -> Siemens PCS7)
S7-400, Siemens PCS7
REPUBLIC OF SLOVENIA
25 Javni holding Ljubljana d.o.o. Migration of boiler plant control system blocks 1 and 2 TE-TOL (Siemens Teleperm M - Siemens SPPA T3000)
Siemens Teleperm M, Siemens SPPA T3000
REPUBLIC OF SLOVENIA
26 Javni holding Ljubljana d.o.o. Multiple migration of boiler plant control system of block 3 TE-TOL (Siemens Teleperm M - Siemens PCS7, Siemens SPPA T3000)
Siemens Teleperm M, Siemens SPPA T3000, Siemens PCS7
REPUBLIC OF SLOVENIA
27 HEP Proizvodnja d.o.o. Connection of VK5 and VK6 hot water boilers to the superior control system Siemens SPPA T3000
Siemens SPPA T3000
CROATIA
28 Javni holding Ljubljana d.o.o. Realization of coal and biomass transport management system TE-TOL
Siemens PCS7
REPUBLIC OF SLOVENIA
29 INA d.d. Modernization of the management system PV6
Siemens PCS7
CROATIA
30 INA d.d. Migration of wastewater treatment control system in oil refinery Sisak (Krofta) (Siemens PCS7 V6 -> Siemens PCS7 V7) Siemens PCS7
CROATIA
31 Žito d.o.o. Upgrading the production management system for organic feed in the plant TSH Vitalka
Siemens S7-300, WinCC
CROATIA
32 Žito d.o.o. Realization of oilseed crossing control system in Čepin oil factory plant
Siemens S7-300, WinCC
CROATIA
33 Kandit d.o.o. Realization of control system for chocolate filling machine "Cavemil"
Siemens S7-300
CROATIA
34 HEP Plin d.o.o. Telemetry monitoring system for measuring and reducing and odorization stations
Siemens S7-300, Siemens SINAUT Micro SC
CROATIA
35 ČEZ a.s. Replacement of burner control systems in plants B5 and B6 TE Varna
Siemens SPPA T3000
REPUBLIC OF BULGARIA
36 HEP Proizvodnja d.o.o. Realization of the heat battery management system in the EL-TO Zagreb plant (capacity 1 GWh)
Siemens SPPA T3000
CROATIA
37 Kosovo Energy Corporation j.s.c. Replacement of electrostatic filter control systems in plants B4 and B5 TE Kosovo A
Siemens SIFUPIC F, Siemens WinPic
REPUBLIC OF KOSOVO
38 HEP Proizvodnja d.o.o. Replacement of electrostatic filter control system in TE Plomin 1
Siemens SIFUPIC F, Siemens WinPic
CROATIA
39 Kosovo Energy Corporation j.s.c. Replacement of the chemical water preparation management system at the TE Kosovo B
Siemens PCS7
REPUBLIC OF KOSOVO
40 HEP Proizvodnja d.o.o. Migration of KPV (chemical water preparation) management system in the plant TE-TO Osijek (Siemens PCS7 V6 -> Siemens PCS V8)
Siemens PCS7
CROATIA
41 Tvornica šećera Osijek d.o.o. Replacement of the control system of boiler plant 4490 within sugar factory Osijek d.o.o.
Siemens S7-300 F, Siemens S7-1500
CROATIA
42 Tvornica šećera Osijek d.o.o. Replacement of cooling tower management system in the power plant of Sugar Factory Osijek d.o.o.
Siemens S7-1500, WinCC Professional
CROATIA
43 Tvornica šećera Osijek d.o.o. Replacement of the lime kiln management system within the sugar factory Osijek d.o.o.
Siemens S7-1500, WinCC Professional
CROATIA
44 Glazir d.o.o. Realization of the plant management system for the production and packaging of fruit fillings and other bakery fillers
S7-300, WinCC Flexible
CROATIA
45 Coca-Cola HBC Ireland Ltd. Realization of the steamer management system at the Coca-Cola HBC Lisburn plant
S7-300, WinCC Flexible, ProTool
UNITED KINGDOM
46 Coca-Cola HBC Eurasia OOO Realization of the steamer management system at the Coca-Cola HBC Novosibirsk plant
S7-300, WinCC Flexible, ProTool
RUSSIAN FEDERATION
47 Pivara Tuzla d.o.o. Migration of the brewing monitoring and management system (Brewmaxx ProLeiT 8 -> Brewmaxx ProLeiT 9)
Siemens S7-400, Brewmaxx ProLeiT
REPUBLIC OF BOSNIA AND HERZEGOVINA
48 PepsiCo Inc. Realization of kvass production management system at PepsiCo Domodedovo plant Siemens S7-400 H, Siemens PCS7, Siemens APF, Siemens APF TP
RUSSIAN FEDERATION
49 Dashen Beer S.C. Automation of brewery cold block Dashen Debre Birhan (Ethiopia) S7-400, Brewmaxx ProLeiT
ETHIOPIA
50 AB InBev Ltd. Automation of brewery cold block Sagamu (Nigeria)
S7-400, Brewmaxx ProLeiT
NIGERIA
51 Brasserie Heineken Schiltigheim S.A. Migration of beer filtration control system (PROCOS -> Brewmaxx ProLeiT)
S7-400, Brewmaxx ProLeiT, PROCOS
FRANCE
52 Našički vodovod d.o.o. Design and implementation of the water supply system of settlement Valenovac
S7-1200, WinCC
CROATIA
53 Vodovod Osijek d.o.o. Realization of the management system of the regional water supply system of the city of Osijek
CROATIA
54 Tvornica šećera Osijek d.o.o. Design and realization of the technological wastewater treatment system within the sugar factory Osijek d.o.o.
CROATIA
55 Našički vodovod d.o.o. Reconstruction and extension of the Velimirovac water well (Q=150L/s)
S7-300, WinCC Flexible
CROATIA
56 HEP Toplinarstvo d.o.o. Technical and economic optimization of district heating systems
WinCC, Petrol TERMIS
CROATIA
57 Miholjački vodovod d.o.o. Design and realization of wastewater treatment plants of the city Donji Miholjac
Siemens S7-300, Siemens Water Libraries
CROATIA
58 Miholjački vodovod d.o.o. Reconstruction of the Donji Miholjac water well to increase the capacity of water treatment with ultrafiltration plant (45L/s)
Siemens S7-300, WinCC, WinCC Flexible
CROATIA
59 Đakovački vodovod d.o.o. Preparation of project documentation and realization of supervision and management system for 52 line facilities of the public drainage system of the city of Đakovo Siemens S7-1200, Siemens S7-1500, WinCC, WinCC Redundancy, Grundfos WWT
CROATIA
60 Dvorac d.o.o. Preparation of project documentation and realization of supervision and management system for 52 line facilities of the public drainage system of the agglomeration of the cities of Belišće and Valpovo
Siemens S7-1200, WinCC Professional, Grundfos WWT
CROATIA
61 Žito d.o.o. Reconstruction of the system of supervision and management of the Đakovština corn mill
Siemens S7-300, WinCC Flexible
CROATIA
62 Vodovod grada Vukovara d.o.o. Design and implementation of the system of supervision and management of new water reservoir 2x1500m3
Siemens S7-300, WinCC
CROATIA
63 Vukovarsko-srijemska županija Design and implementation of the irrigation monitoring and management system of the area Sopot
Siemens S7-1200, WinCC Professional
CROATIA
64 Vukovarsko-srijemska županija Design and implementation of the system of monitoring and management of irrigation area Blato-Cerna
Siemens S7-1200, WinCC Professional
CROATIA
65 Zora obrt za poljoprivredu Realization of the system of monitoring and management of tansport and storage of grains in the silo in the settlement Sveti Đurađ
Siemens S7-300, WinCC Flexible
CROATIA
66 KIO Keramika d.o.o. Design and implementation of press filling systems
Siemens S7-300
CROATIA
67 HEP Proizvodnja d.o.o. Realization of the system of monitoring and optimization of electricity consumption in plants TE-TO Osijek, TE-TO zagreb, EL-TO Zagreb i TE Plomin 1 i 2
Siemens S7-300, WinCC, WinCC Powerrate
CROATIA
68 Knauf Insulation d.o.o. Realization of the system of monitoring and optimization of electricity consumption in the plant Knauf Insulation d.o.o. in Novi Marof
Siemens ET200SP, SIMATIC Energy Manager
CROATIA
69 HOPS d.o.o. Monitoring and control of the uninterruptible power supply system of the Network Center Zagreb located in TS Žerjavinec
S7-300, WinCC Flexible
CROATIA
70 HEP Proizvodnja d.o.o. Monitoring and control of uninterruptible power supply system 0.4kV PTE plant in TE-TO Osijek facility with integration into the superior system Siemens SPPA T3000
Siemens S7-300, Siemens SPPA T3000
CROATIA
71 VTTI B.V. Realization of the system of monitoring and management of the process of storage and manipulation of petroleum products
Siemens PCS7, Siemens PCS7 Safety Matrix
CROATIA
72 Gradska toplana d.o.o. Realization of the system of supervision and management of 173 thermal substations in the city of Karlovac. Integration of the system for dynamic modeling of hot water pipelines AVEVA TERMIS
Schneider Electric M172P, Schneider EcoStruxure Geo SCADA, AVEVA TERMIS
CROATIA
73 Vodovod grada Vukovara d.o.o. Realization of the system of monitoring and management of the storm and fecal wastewater treatment plant in the city of Vukovar
Schneider Electric M340, Schneider EcoStruxure Geo SCADA
CROATIA
74 Zračna luka Dubrovnik d.o.o. Automation of aviation fuel supply system and internal petrol stations
S7-1500, WinCC Professional
CROATIA
75 Wienerberger d.o.o. Risk reduction of production lines 1 and 2 plants 1 PJ Đakovo in accordance with the Machinery Directive 2006/42/EZ
CROATIA
76 INA d.d. System of monitoring and management of bitumen production in the oil refinery in Sisak
S7-1500, WinCC Professional
CROATIA
77 Petrokemija d.o.o. Fertilizer transport supervisory and control system
S7-1500, WinCC Professional
CROATIA
78 GPP d.o.o. Control and control system of rectifier stations
S7-1200, Končar PROZA NET
CROATIA
79 Creating a P&I diagram of the COVID-19 vaccine factory
COMOS
CROATIA
80 Rafinerija nafte Brod a.d. Circuit breaker and other switching equipment monitoring system
Siemens PCS7
REPUBLIC OF BOSNIA AND HERZEGOVINA
81 HEP Proizvodnja d.o.o. Services of preventive regular and corrective maintenance of power equipment of TE Plomin 1
Siemens Teleperm XP (TXP), Siemens SPPA T3000
CROATIA
82 HIŠ d.o.o. Development of supervisory and control system for wastewater treatment plant within sugar factory Županja
S7-400, WinCC
CROATIA
83 Belišće d.d. Realization of PCS-7 secondary control system at the power plant of paper factory Belišće d.d.
Siemens PCS7
CROATIA
84 Šećerana a.d. Šajkaška Žabalj Realization of the control system of vertical sugar crystallizer
Siemens PCS7
REPUBLIC OF SERBIA
85 Varkom d.o.o. Development, testing and commissioning of the telemetry water supply system of the City of Varaždin and Varaždin County
S7-300, WinCC, Web Navigator, SINAUT ST7-CC
CROATIA
86 Belišće d.d. Design, development of PCS7 and WinCC SCADA applications, execution, testing and commissioning of the control system for chemical water preparation within the paper factory Belišće d.d.
Siemens PCS7
CROATIA